Rajasthan net-metering policy 2015
The net metering policy for Rajasthan went into force on 26th of February 2015. The eligible parties installing rooftop PV installations are allowed to benefit from the net metering tariff of INR 7.5 per installed unit.The policy restricts the cumulative installation that can take place at any particular distribution transformer to 30% of the transformer's capacity. There are also restrictions on the size of the rooftop plant that can be set up by an individual consumer: it cannot exceed 80% of the sanctioned connected load. The lower threshold for the plant size is pegged at 1kW and the upper limit is 1MW.
Want to know more about this policy ? Learn more