The Australian government, through the Australian Renewable Energy Agency (ARENA) and its Advancing Renewables Program, is providing AUD 15 million to a concentrated solar project with thermal hydro storage.
The flagship project has a 4 MW solar capacity and 3 MW / 50 MWh storage capacity. The manufacturing facility will also be expanded to allow for future project deployment.